CAPMMedium
CAPM Practice: Demonstrate an understanding of a project management plan schedule
A project activity has three expert estimates: Optimistic = 4 days, Most Likely = 6 days, Pessimistic = 14 days. Using PERT, what is the expected duration?
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free