CAPM Practice: Demonstrate an understanding of a project management plan schedule
A schedule management plan states that a 10% or more schedule variance triggers a corrective action review. At the current reporting period, the schedule variance is -12%. What is the APPROPRIATE next step?
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).