CAPM Practice: Demonstrate an understanding of a project management plan schedule

A project manager is reviewing the project schedule and identifies a path that has 5 days of float. Two weeks later, after some project changes, the same path now has only 1 day of float. What has happened?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).