CAPM Practice: Demonstrate an understanding of a project management plan schedule
A project manager is analyzing schedule performance at the midpoint of a 12-month project. PV = $600,000, EV = $480,000, AC = $520,000. A subcontractor just notified her they will deliver a critical component 4 weeks late. How should the project manager respond?
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).