CAPM Practice: Demonstrate an understanding of a project management plan schedule

A project manager is creating a schedule for a 6-month construction project. She has defined 120 activities, estimated all durations, identified dependencies, and loaded resources. The initial schedule shows the project finishing in 8 months — 2 months over the required deadline. What is the CORRECT sequence of actions to compress the schedule?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).