CAPM Practice: Demonstrate an understanding of a project management plan schedule
A project manager analyzes the schedule network and identifies that two paths both have 0 float. Path A includes 8 activities; Path B includes 12 activities. Both paths end at the same project completion milestone. How does this dual-critical-path situation affect project risk?
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).