CAPM Practice: Demonstrate an understanding of a project management plan schedule

A project manager has a project with a critical path of 120 days. She uses Monte Carlo simulation and finds there is only a 30% probability of completing the project in 120 days. The 80th percentile shows 140 days. What does this analysis recommend?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).