CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Halima Menon facilitated a two-hour problem-solving meeting at Vector Aerospace to address recurring quality issues. Three team members dominated the discussion while four others barely spoke. The meeting ran 30 minutes over, and no decisions were made. When evaluating this meeting's effectiveness, what is the PRIMARY concern?
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).