CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

A scatter diagram shows a strong positive correlation between the number of code review hours and the number of bugs found. A project manager concludes that increasing code review hours will always find more bugs. What is WRONG with this conclusion?

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).