CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

A project manager facilitates a lessons learned session at project close. Some team members resist sharing negative experiences due to fear of blame. What approach BEST addresses this challenge?

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).