CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

A project manager applies the 80/20 rule and discovers that 3 out of 15 defect categories account for 78% of all defects. She decides to focus all improvement resources on those 3 categories. A stakeholder challenges this, arguing the other 12 categories are also important. What is the BEST response?