CAPMMedium
CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
A project manager wants to identify all stakeholders' positions and concerns before addressing a complex organizational problem. She distributes questionnaires to experts, collects anonymous responses, shares a summary with all experts, and repeats the cycle until responses converge. This describes:
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).