CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Wanjiku Morita at Maple Ridge Corp is selecting problem-solving tools for different project situations. Match each situation on the left with the most appropriate technique on the right.
Items:
1. Identifying root causes of recurring production defects
2. Quickly generating solution options for a budget constraint
3. Understanding customer satisfaction with a new service
4. Daily coordination of development team activities
Which option correctly matches each item to its description?
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).