CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

A project manager applies trend analysis to schedule performance data across six reporting periods. She notices the Schedule Performance Index (SPI) decreasing each period: 1.05, 0.98, 0.91, 0.85, 0.79, 0.73. What conclusion is MOST supported?

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).