CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

During project execution, a team member reports a problem that is blocking their work. The project manager applies the 5 Whys and discovers the real cause is an unclear requirement from the original project brief. This demonstrates that the 5 Whys technique:

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).