Felipe Ogawa conducted a brainstorming session at Warden Defense, but participants spent most of the time critiquing each idea as it was presented. Many team members stopped contributing. What mistake did Felipe make?
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).