CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

A project team is using root cause analysis and identifies two contributing causes: (1) inadequate testing time due to schedule pressure, and (2) unclear test specifications. These are BEST categorized as:

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).