CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

Meera Hayashi at Vector Aerospace notices that team meetings consistently run over time, decisions are rarely documented, and the same topics are revisited weekly. What is the MOST effective way to evaluate whether these meetings are productive?

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).