CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
A project manager observes that the same type of quality defect appears repeatedly across multiple deliverables. After documenting it in the issue log, what should be the NEXT step?
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).