CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

A check sheet records the following defect tallies over one week: Installation Error (||||| ||||| ||), Measurement Error (||||), Documentation Error (||||| |||||). Which defect type is most frequent?

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).