CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
During a project, the team identifies that deliverable defects are increasing. The project manager creates a diagram that maps potential causes under categories such as 'People,' 'Process,' 'Equipment,' and 'Environment.' Which tool is being used?
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).