Vesna Escobar is working on a project at Kilowatt Power. She needs to understand the distinction between the project management plan and the product management plan. What is the PRIMARY difference?
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).