CAPM Practice: Demonstrate an understanding of project management planning
Haruki Kessler is planning resources for a mobile app development project at Quartile Advisory. The project requires 3 developers for 6 months, 1 designer for 3 months, and 1 tester for 4 months. What is the total number of resource months needed?
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).