CAPM Practice: Demonstrate an understanding of project management planning
Zuri Haddad is planning a manufacturing process improvement project at Forgepoint Manufacturing. She has identified the need for 3 mechanical engineers (full-time for 4 months), 2 quality specialists (half-time for 6 months), and 1 production supervisor (consulting 10 hours per week). What should Zuri do FIRST to determine if these resources are available?
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).