CAPM Practice: Demonstrate an understanding of project management planning

Sekou Fuentes is reviewing the project management plan for a software migration project at Goldleaf Brands. What is the PRIMARY purpose of the risk section in the project management plan?

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).