CAPM Practice: Demonstrate an understanding of project management planning

Zoran Fujimoto is reviewing project documents and notices that one document outlines how the team will manage scope, schedule, and costs, while another describes the product's technical specifications. What is the PRIMARY distinction between these two documents?

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).