CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Valentina Baranov is leading a software upgrade project at Kilowatt Power. A key stakeholder requests a major scope change that would require additional funding. Who is primarily responsible for approving this additional funding?
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).