CAPM Practice: Demonstrate an understanding of project roles and responsibilities

Declan Pemberton is leading a product development project at Trailhead Partners. Two team members are in conflict about the technical approach. Declan listens to both perspectives, asks clarifying questions, and helps them find common ground. Which project manager role is Declan demonstrating?

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).