CAPM Practice: Demonstrate an understanding of project roles and responsibilities

Astrid Shimizu is the project manager for a software implementation at Aether Systems. The project sponsor asks Astrid to provide weekly status updates and escalate any issues that could affect the project budget or timeline. What is the PRIMARY distinction between Astrid's role and the sponsor's role?

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).