CAPM Practice: Demonstrate an understanding of project roles and responsibilities

During a project retrospective at Basalt Digital, Mila Baranov asks her team about her effectiveness as a project manager. A team member says, 'You're great at listening to our concerns and helping us grow our skills.' Which project manager role is being highlighted?

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).