CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Zuri Reddy, a project manager at Gridstone AI, notices that a team member is frustrated because their ideas are not being heard in meetings. Zuri schedules a one-on-one meeting to understand the team member's concerns and helps them prepare to present their ideas more effectively. Which project manager role is Zuri demonstrating?
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).