CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Amina Horvat is leading a project at Lodestar Engineering when two team members disagree on the technical approach. Amina listens to both perspectives, asks clarifying questions, and helps the team members find common ground. Which project manager role is Amina primarily demonstrating?
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).