Skip to content
CAPMMedium

CAPM Practice: Demonstrate an understanding of project roles and responsibilities

Arun Pemberton, a project manager at Vector Aerospace, notices that his sponsor keeps making technical decisions that should be made by the project team. What should Arun do?

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free