CAPM Practice: Demonstrate an understanding of project roles and responsibilities
During a project status meeting at Monolith Build Co, a team member asks Valentina Obi to clarify the difference between her role as project manager and the role of a manager in the organization. What is the PRIMARY distinction?
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).