CAPM Practice: Demonstrate an understanding of project roles and responsibilities

Solange Bose, a project manager at Maple Ridge Corp, is preparing for a project kickoff meeting. The project sponsor asks Solange to clarify their respective roles. What is the PRIMARY responsibility that distinguishes the project sponsor from the project manager?

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).