CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Kavya Brandt at Basalt Digital is managing a website redesign project with evolving requirements. The customer provides feedback after each sprint, and the team adapts the design accordingly. What type of approach is Kavya using?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).