CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Divya Ogawa at Lumen Solar is reviewing project documentation and notices the scope statement includes 'Install solar panels on all residential buildings in the district.' After consulting with stakeholders, she learns there are 47 buildings but only 40 will receive panels due to structural limitations. The timeline assumes all 47 buildings. What should Divya do FIRST?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).