CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Arun Lindqvist is reviewing a project scope statement for a construction project at Monolith Build Co. The statement includes detailed technical specifications, acceptance criteria, and deliverables. However, he notices the document does not clearly state what is excluded from the project. What is the MOST significant risk of this omission?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).