During project planning at Joule Energy, Matthias Haugen identifies that 'the vendor will deliver equipment by June 1' and 'regulatory approval may be delayed due to pending legislation.' He also notes 'the project must not exceed the $2M budget' and 'a key supplier may face labor strikes next quarter.' How should Matthias categorize these four items?