CAPM Practice: Demonstrate an understanding of the various project life cycles and processes

Tariq Ogawa is leading a software development project at Halcyon Networks. The client requirements keep changing based on user feedback after each iteration. What type of approach is BEST suited for this project?

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).