Isabella Morita is leading a six-month initiative at Gridstone AI to develop a new customer portal. Her manager asks if this is a project or an operation. What is the PRIMARY characteristic that defines this as a project?

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).