CAPM Practice: Demonstrate an understanding of the various project life cycles and processes

Amala Delgado is leading a project to implement a new inventory system at Harvest Market Co. The CFO asks her to also optimize the company's procurement processes and manage the ongoing IT support operations. What should Amala explain to the CFO?

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).