CAPM Practice: Demonstrate an understanding of the various project life cycles and processes

Samir Virtanen is managing a software upgrade at Keystone Structures. The upgrade will take 6 months, has a defined budget, and will end once the new system is operational. His colleague manages ongoing IT support with no defined end date. What is the PRIMARY distinction between these two efforts?

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).