CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Amala Iyer is reviewing the project charter for Kilowatt Power's new substation project. The sponsor lists several items as project risks, but Amala notices some appear to be constraints instead. A statement reads: 'The project must be completed by December 31 to meet regulatory requirements.' What should Amala identify this as?