CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Marisol Haugen is a project coordinator at Goldleaf Brands supporting a new product line launch. During stakeholder interviews, she learns that senior leadership expects the project to transform how the company engages with customers, moving from traditional retail to digital channels. The CFO expresses concern about the significant organizational change required. How does this project serve as a vehicle for change?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).