CAPM Practice: Demonstrate an understanding of the various project life cycles and processes

Camilo Sabbagh is reviewing the project charter for a digital transformation initiative at Quartile Advisory. He notices the project scope section lists 'implement new CRM system, train all staff, and improve customer satisfaction by 25%.' A colleague asks Camilo if this scope statement is appropriate. What is the BEST response?

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).