Nadia Shimizu is reviewing a project charter for a mobile app development project at Joule Energy. The charter states the project will 'improve customer satisfaction' and 'enhance user experience.' What is the PRIMARY concern with this project scope definition?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).