CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Sunil Sokolov is managing a software implementation at Wavelength Biotech. During planning, the team documented that the vendor will provide training materials by Month 3, though this has not been confirmed in writing. The regulatory approval timeline is fixed and cannot change. A competitor's similar product launch may impact adoption. What has Sunil's team documented?