CAPMHard
CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Nadia Kwon is leading a digital transformation project at Quasar Media. The CEO asks her to expand the project scope to include additional features that were not in the original business case. Nadia knows this will delay delivery and exceed the budget, but the CEO insists it must be done without additional funding. According to the PMI Code of Ethics, what should Nadia do?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).