Amina Korhonen is leading an initiative at Harvest Market Co to replace the company's legacy inventory system. She is also aware that her manager oversees multiple related initiatives, including warehouse automation and supplier integration. What is the PRIMARY difference between Amina's project and her manager's responsibility?